Nearing Completion Of Mono Way And Greenley Road Widening Project

Sonora, CA — George Reed Construction is planning to begin the paving of areas in and around the Mono Way and Greenley Road intersection on Monday evening.

Work this week will take place during the overnight hours between 7pm-7am. The paving is expected to be finished by early Friday morning, November 10. Paving will specifically occur on Mono Way from 300 ft. east of Greenley Road to 300 ft. west of Barretta Street, on Sanguinetti Road from Mono Way to Greenley Road, and on Greenley Road from Guzzi Lane to Sanguinetti Road.

Be prepared for lane closures and 10-minute traffic delays during the work hours.

Final pavement striping is scheduled for November 13-16, also during the overnight hours.