Caltrans Week Of April 20 Work Plans

Sponsored by:

Stockton, CA — Caltrans will be setting up work zones on six Mother Lode highways next week.

In Calaveras County, along Highway 4, paving each weekday will focus between Main Street/Douglas Flat and Meko Drive from 6 a.m. until 5 p.m., with one-way traffic control and possible ten-minute motorist delays.

On Highway 12, each weekday, utility crews will be working between Pine Street and Cosgrove Creek from 7 a.m. until 5 p.m. with one-way traffic controls in place and possible five-minute delays.

Utility work on Highway 26 all week between Hogan Dam Road and West Highway 12 is scheduled from 7 a.m. until 5 p.m. with one-way traffic control and five-minute delays possible.

In Calaveras County on Highway 49, utility crews will work Monday between Six Mile Creek and Park Avenue/Sonora Street from 9 a.m. until 5 p.m. with one-way traffic control and possible five-minute delays. On Tuesday, from 9 a.m. until 5 p.m. the crew will be working between Mayo Road and Highway 4/Finnegan.

In Tuolumne County, along Highway 108, all week long construction work along the shoulders will run from Sullivan Creek and Peaceful Oak Road beginning at 6 a.m. and picking up about 7 p.m., causing possible minor delays. Night time construction work on Highway 108 Monday through Friday between Sullivan Creek and Peaceful Oak Road is scheduled from 7 p.m. until 6 a.m. with possible ten-minute delays.

Tuesday, along Highway 108, Caltrans will be doing a drainage inspection between Middle Camp Sugar Pine and Sugar Pine roads from 8 until 10 a.m. There will be one-way traffic control and possible minor delays.

On Highway 120, in Tuolumne County, Sunday through Friday nights into the early morning hours, striping operations are planned between Green Springs and Perricone roads. The scheduled work times will run from 10 p.m. and 6 a.m. Motorists should plan for possible ten-minute delays.

Along Highway 120, Monday and Tuesday, a sweeping crew will work between the Fire Station and Cherry Valley Road from 8 a.m. until 3 p.m. with possible minor delays. Wednesday and Thursday, the sweeping crew will be working between Cherry Valley Road and West Boundary Yosemite Park, from 8 a.m. until 3 p.m.